Back to the FAQ

How do I enable High Integrity in Plan-IT Workshop?

Enabling High Integrity in Plan-IT means that when you save and modify work orders, Plan-IT performs an extra check before it writes to the database.

This can help prevent indexing problems with some networks.

When you have the latest version of Plan-IT (from version 5.171.7100) you can enable this option.

  1. In the menubar, click on the option Systeem
  2. Select the option Management.
  3. Click with the right mouse button on the green Plan-IT bar and select the option Systemsettings.
  4. Put a check in the box with the option High Integrity.

After you have enabled this option, all users have to close and restart Plan-IT for the changes to take effect.

Keep in mind that Plan-IT may become a bit slower because it will perform extra checks on the database.



Back to the FAQ